SOW BT-STC-Q2-2026 • Status Update • May 4, 2026

Q2 2026 Growth System — Project Status

6 of 11 emails sent • WS3 Meta Ads built — awaiting Rob approval • WS4 automation overdue since Apr 27 • WS1B Phase Zero not yet started
Report Date: May 4, 2026
SOW Value: $17,000 + $5,500 (Quo)
Contract: BT-STC-Q2-2026
Days Remaining: 57 (to Jun 30)
WS1A Security: Complete
WS1B Phase Zero: Not Started
WS2 Email: Active — 6/11 Sent
WS3 Meta Ads: Awaiting Approval
WS4 Automation: OVERDUE
Quo SOW: Confirm Signature

Where We Stand — May 4, 2026

WS1A (Security) is the only workstream fully complete. WS2 (Email) is on track — 6 of 11 emails sent on schedule, with Email 5 (Member Offer) due May 7. WS3 (Meta Ads) is built and ready to launch; all three campaigns are complete with final creative and targeting, but Rob's approval has been pending since April 28. WS4 (Automation) is the most critical gap — both sequences were due April 27, 7 days ago, and are not yet live. WS1B (Phase Zero Design) has not started, 14 days past its planned April 20 start, with a June 1 deadline that is now 28 days out.

The Quo phone system SOW was deployed April 21 for Rob's signature by ~April 25. That deadline has passed — status needs confirmation. If not yet signed, the May 22 go-live target is at risk given the number porting timeline.

🔴 WS4 Automation — 7 Days Overdue: Both sequences (Estimate Lead Warmup + Club Welcome) were due April 27. Neither is live. The Kit sequence "Estimate Lead Warmup" does not yet exist. Email content must be pasted via UI; Zapier zaps must be built. This is the most urgent open item.

⚠ Email 5 Due May 7 (3 Days): WS2 Email 5 (Member Offer, Kit ID 23674286) sends ~May 7. The HTML has not been pasted into Kit yet. This needs to happen today or tomorrow.

🔴 WS1B Phase Zero — 14 Days Past Start: Planned start was April 20. No work has begun. June 1 deadline is 28 days away. Design comps for 3 pages (Homepage, Services Hub, Estimate/Contact) must be delivered with one revision round. Need to begin this week.

Workstream 1A
Security Hardening
CompleteApr 10 ✓
SOW value: $3,500 (shared with WS1B). All deliverables confirmed live.
  • WordFence Premium — installed, firewall configured, real-time defense live
  • 2FA enabled for all WordPress admin users
  • Plugin audit complete — unused removed, outdated updated
  • Automated daily backups + off-site copy; restore test documented
  • Full malware/vulnerability scan; findings remediated
  • GA4 event tracking + Meta Pixel + Lead conversion event live
  • Security Checklist deliverable published
100% complete
Workstream 1B
Phase Zero Design
Not StartedDue Jun 1
SOW value: $3,500 (shared with WS1A). Site architecture + design comps for 3 pages. Planned start: Apr 20 — 14 days ago.
  • Site feature architecture — estimate flow, service LPs, Club section, trust signals, service area map
  • Design comp: Homepage
  • Design comp: Services Hub
  • Design comp: Estimate/Contact
  • AI-generated images available; photo shoot still pending
  • One revision round + final delivery by Jun 1
0% complete — 28 days to deadline
Immediate Next StepBegin site architecture brief this week. 28 days is tight for 3 design comps + revisions.
Workstream 2
Q2 Member Email Campaign (11 Emails)
ActiveThrough Jun 24
SOW value: $3,500. Apr 1–Jun 24. Residential and commercial versions. 6 of 11 sent.
  • Email 1 — Spring Kickoff: SENT ~Apr 7
  • Email 2A — Residential Pruning: SENT Apr 16
  • Email 2B — Commercial Assessment: SENT Apr 16
  • Email 3 — Five Things: SENT Apr 23
  • Email 4A — Social Proof (Residential): SENT Apr 28
  • Email 4B — Social Proof (Commercial): SENT Apr 28
  • Email 5 — Member Offer (ID 23674286): Due ~May 7 — HTML NOT PASTED
  • Email 6 — Testimonials: ~May 14
  • Email 7 — Urgency: ~May 21
  • Emails 8–11: May 28 – Aug
6 of 11 emails sent (55%)
Urgent: Paste Email 5 HTML by May 6Kit ID 23674286. Subject: "Club Members: Spring Pruning Special — Book This Week". Paste via Kit editor before May 7.
Workstream 3
Meta Paid Social Advertising
Awaiting ApprovalThrough Jun 30
SOW value: $7,500 + ad spend at cost. All 3 campaigns built. Rob approval is the only blocker.
  • Meta Business Manager access confirmed
  • Meta Pixel + Lead event live at sperrytreecare.com
  • Spring Pruning LP redesigned at /spring-estimate/
  • Lead Gen campaign: native 9:16 + 1:1 images, 29-zip targeting, age 35–65+
  • Retargeting campaign: built and ready
  • Local Awareness campaign: built and ready
  • Campaign approval page live — sperry-meta-approval-apr2026.jason-8ce.workers.dev
  • Rob approval pending since April 28 — no response yet
  • Publish all 3 campaigns once approved
  • Monthly performance reports (May, Jun, Q2 wrap)
Build complete — launch blocked on client approval
Blocked: Rob Approval RequiredReview at sperry-meta-approval-apr2026.jason-8ce.workers.dev. Campaigns publish same day as approval.
Workstream 4
Lead Warming + Club Welcome Automation
OVERDUE — Apr 27
SOW value: $2,500. Both sequences due April 27 — 7 days ago. BT handles all Kit + Zapier setup.
  • Automation design doc complete
  • 6 sequence email drafts written
  • /estimate-sent/ page live; Lead event active
  • Paste guide published at sperry-sequence-setup-apr2026.jason-8ce.workers.dev
  • Create "Estimate Lead Warmup" sequence in Kit (does not exist yet)
  • Paste 3-email lead warming content into Kit UI
  • Paste 4-email Club welcome content into Kit UI (sequence ID 2627196)
  • Configure Zapier: Jobber "Estimate Created" → Kit lead warmup enrollment
  • Configure Zapier: Kit "Tree Care Club Member" tag → welcome sequence
  • End-to-end test + go-live
Design 100% done — configuration 0% done
Immediate Action RequiredThis is the highest-priority overdue item. Full build + test should take 2–3 hours. Use paste guide at sperry-sequence-setup-apr2026.
Quo Phone System
OpenPhone + Sona AI Receptionist
Confirm SignatureGo-Live May 22
SOW BT-STC-QUO-2026, $5,500 flat. Rob signature was due ~Apr 25 — 9 days ago. May 22 go-live requires porting, which takes 2–4 weeks.
  • SOW scoped + deployed at sperry-quo-sow-apr2026.jason-8ce.workers.dev
  • Rob signature — status unknown (was due ~Apr 25)
  • Carrier account number + PIN for number porting (Sperry provides)
  • WS1: Account setup + port initiation
  • WS2: Sona AI receptionist configuration
  • WS3: Zapier Quo→Jobber→Kit integration
  • WS4: 10 DLC SMS registration (2–4 week FCC window)
Confirm with RobIf SOW is not yet signed, May 22 go-live is at risk. Number porting alone takes 2–4 weeks from initiation.
DateEmailKit IDAudienceStatus
Apr 7Email 1 — Spring Kickoff23610364All Club MembersSENT
Apr 16Email 2A — Residential Pruning23610791All Club MembersSENT
Apr 16Email 2B — Commercial Assessment23657210Commercial tagSENT
Apr 23Email 3 — Five Things23610365All Club MembersSENT
Apr 28Email 4A — Social Proof (Residential)23859665Residential (~1,023)SENT — Verify
Apr 28Email 4B — Social Proof (Commercial)23852851Commercial (~359)SENT — Verify
May 7Email 5 — Member Offer23674286All Club MembersHTML NOT PASTED
May 14Email 6 — Testimonials23674287All Club MembersStub Only
May 21Email 7 — Urgency23674289All Club MembersStub Only
May 28Email 8 — Hidden Risks23674290All Club MembersStub Only
Jun 4Email 9 — Summer Tree Care23674291All Club MembersStub Only
Jun 11Email 10 — Referral23674293All Club MembersStub Only
Jun 18Email 11 — Tree Removal23674296All Club MembersStub Only

Note — Emails 6–11 (stub only): All remaining email stubs (IDs 23674287–23674298) have Kit broadcast placeholders but no HTML content. Each needs to be loaded via Kit's Custom HTML editor before its send date. The upgraded templates are ready locally. Paste schedule: load Email 6 by May 13, Email 7 by May 20, etc.

PaymentAmountDue DateStatus
Kickoff Deposit$4,500Mar 26, 2026Received
Payment 2$2,083.33Apr 1, 2026Due — Confirm
Payment 3$2,083.33May 1, 2026Due — Confirm
Payment 4$2,083.33Jun 1, 2026Upcoming
Payment 5$2,083.33Jul 1, 2026Upcoming
Payment 6$2,083.33Aug 1, 2026Upcoming
Final Payment$2,083.33Sep 1, 2026Upcoming
Quo SOW Invoice 1$2,750On signingPending Signature
Quo SOW Invoice 2$2,750Go-live (May 22)Planned